Biogas-JurongWRP

Project Details

Client: PUB
Scope of Work: Jurong Water Reclamation Plant Phase 4 Expansion – Contract 2 (Solids): Supply and installation of Thermo Hydrolysis Sludge Treatment Plant, with Dewatering Centrifuge, Biogas Steam Boilers and Chemical Dosing Equipment
Time Period: 18 months
Contract Value: $16.6 m
Completion Date: Oct 2016

Client: PUB
Scope of Work: Supply and Installation of Gas Engine Generator Sets To Produce Electricity From Biogas at Jurong WRP (3MW)
Time Period: 13 months
Contract Value: $7.5 m
Completion Date: February 2015

Client: PUB
Scope of Work: Supply and Installation of Biogas Engine Generator at Changi WRP (2MW)
Time Period: 18 months
Contract Value: $6.8 m
Completion Date: June 2015